First you will need to
determine the size of the patio, lay it out with string & stakes,
taking into consideration your stone type (dimensional or random sizes)
and the pattern you will be using.
Step 2: Excavate area to the depth of approximately 6” - 10”. Step 3: It is advised to have a 2” - 3” gravel base. Level and pack down firmly. Step 4: You will need to pour 3” - 4” concrete, re-inforced with rebar. When concrete is beginning to set, take a broom or rake to roughen up the surface to aid in the adhesion of the stone and mortar. Step 5: Set stones atop mortar, leaving 1/2” joint spaces between stones. Avoid placing stones with long lines of joints that are continuous (depending on you particular pattern you are using).
|
|||||||
| Stone Plus Mortar | } 1"-3" |
}6"-9" |
|||||
| Concrete Slab | } 3"-4" | ||||||
| Gravel Base | } 2"-3" | ||||||
|
Step 6: Tap with rubber mallet to assure each stone is level and into place. Compensate thinner or thicker stones with adding or removing mortar beneath them. |
|||||||
|
Please consult your stone Mason |
|||||||